PRE-LICENCE PERIOD, BEFORE CONSTRUCTION
• Permits from Authorities
• Preliminary Permit from Forestry
• Grid Connection agreement with TEİAŞ.
• Military permit
• TIA (TEA) Technical Impact Alaysis by TÜBİTAK
• EIA (ÇED) Environmental Impact Analysis
• Maps preparations
• Soil exploration
• Construction permit from Municipality or Ministry.

LICENCE PERIOD, CONSTRUCTION
• Final Permit from Forestry
• Expropriation
• Ornithology report
• Carbon Certificate
• Verification of construction and electrical projects
• WTG purchasing period
o RFQ preparation, collecting offers
o Final terms statements
o Feasibility studies and comparison reports
o Warranties and conveniences
o Contract
• Contracts and Monitoring construction and electrical works
• Inspection and Reporting construction and electrical works
• Commissioning